Standard Operating Procedure for Inert Gas Purging (Nitrogen Blanketing) in API Manufacturing

Department API Manufacturing
SOP No. SOP/API/032/2025
Supersedes SOP/API/032/2022
Page No. Page 1 of 10
Issue Date 13/04/2025
Effective Date 15/04/2025
Review Date 13/04/2026

1. Purpose

To define a standard and safe procedure for performing inert gas purging using nitrogen in API manufacturing processes to protect reactive or moisture/oxygen-sensitive compounds and ensure operator and product safety.

2. Scope

This SOP is applicable to all nitrogen purging operations during synthesis, transfer, storage, or packaging of intermediates and APIs within the API manufacturing facility.

3. Responsibilities

4. Accountability

The Production Manager is accountable for compliance with this SOP. The QA Manager is responsible for reviewing logs and ensuring alignment with GMP and safety guidelines.

5. Procedure

5.1 Prerequisites

  1. Ensure nitrogen cylinder/bulk supply is connected to the distribution manifold.
  2. Check:
    • Pressure gauge (input and output)
    • Flow meter calibration
    • Integrity of hoses and valves
  3. Verify nitrogen purity ≥ 99.5% and ensure the cylinder label is valid.
  4. Ensure all equipment to be purged is clean, closed, and ready for operation.

5.2 Inert Gas Purging Procedure

  1. Open the main nitrogen cylinder valve slowly to pressurize the line.
  2. Adjust the pressure regulator to the required setting (typically 1.5–2.0 kg/cm² or as per BMR).
  3. Start purging through the designated gas inlet line at the bottom or side of the vessel.
  4. Allow venting from the top vent port to displace air or undesired gases (air sweep method).
  5. Continue purging for the specified time (e.g., 20–30 minutes) or until oxygen analyzer shows < 2% oxygen (if applicable).
  6. Once complete, close inlet and vent valves and maintain a positive nitrogen pressure inside the vessel.
  7. Record the duration, flow rate, pressure, and purge completion time in the “Nitrogen Purging Log” (Annexure-1).

5.3 Maintenance of Nitrogen Blanket

  1. Maintain nitrogen pressure inside sealed reactors or vessels by using back-pressure regulators or surge tanks.
  2. In the case of storage tanks, apply periodic nitrogen top-up based on pressure drops.
  3. Ensure “Nitrogen Blanketed” tags are fixed on relevant equipment.

5.4 Safety Precautions

  1. Always handle nitrogen in well-ventilated areas.
  2. Wear safety goggles, gloves, and masks during purging operations.
  3. Ensure no open flames or reactive materials are nearby.
  4. Confirm purging is complete before any sampling or further processing.

6. Abbreviations

7. Documents

  1. Nitrogen Purging Log (Annexure-1)
  2. Nitrogen Cylinder Usage Record (Annexure-2)
  3. Equipment Pressure Check Sheet (Annexure-3)

8. References

9. SOP Version

Version: 2.0

10. Approval Section

Prepared By Checked By Approved By
Signature
Date
Name
Designation
Department

11. Annexures

Annexure-1: Nitrogen Purging Log

Date Batch No. Equipment ID Start Time End Time Pressure (kg/cm²) Flow Rate (L/min)
13/04/2025 API-202504 R-101 09:00 09:30 1.8 40

Annexure-2: Nitrogen Cylinder Usage Record

Cylinder No. Date Start Pressure (kg/cm²) End Pressure (kg/cm²) Used For Operator
NC-1145 13/04/2025 140 100 Pilot Batch Purge

Annexure-3: Equipment Pressure Check Sheet

Date Equipment ID Pre-Purge Pressure Post-Purge Pressure Leak Observed Remarks
13/04/2025 R-101 0.0 1.6 No OK

Revision History:

Revision Date Revision No. Details Reason Approved By
01/01/2022 1.0 Initial Version New SOP Creation QA Head
13/04/2025 2.0 Added Cylinder Record and Safety Controls Regulatory Compliance QA Head