Standard Operating Procedure for Cleaning of Packing Machines Between Batches

Department Tablet
SOP No. SOP/TAB/245/2025
Supersedes SOP/TAB/245/2022
Page No. Page 1 of 6
Issue Date 01/07/2026
Effective Date 06/07/2026
Review Date 01/07/2027

1. Purpose

The purpose of this SOP is to outline the procedures for cleaning packing machines between batches to ensure they are free from product residues, contaminants, and foreign substances. This ensures the quality and safety of the tablets being packaged and complies with Good Manufacturing Practices (GMP).

2. Scope

This SOP applies to the cleaning of all packing machines used in the packaging process for tablets. The cleaning procedure should be followed between batches, after any machine malfunction, or when a change in packaging material occurs.

3. Responsibilities

4. Accountability

The Production Manager is accountable for ensuring that the cleaning process is carried out between each batch. QC is responsible for inspecting the machine before production resumes to ensure the machine is cleaned thoroughly.

5. Procedure

5.1 Preparation for Cleaning

  1. Ensure the packing machine is turned off and isolated from the power source.
  2. Gather the required cleaning materials, including approved cleaning agents, brushes, cloths, and gloves (Annexure-1).
  3. Check the cleaning instructions for the machine and any specific recommendations from the manufacturer (Annexure-2).
  4. Prepare a cleaning solution that is compatible with the machine materials and product residues (Annexure-3).

5.2 Cleaning the Machine

  1. Begin by wiping down the external surfaces of the machine to remove any dust or visible residue (Annexure-4).
  2. Disassemble the machine components that come into contact with the product (e.g., hoppers, conveyors, sealing equipment) and soak them in the cleaning solution (Annexure-5).
  3. Use brushes and cloths to scrub all internal parts to remove any remaining product residues (Annexure-6).
  4. Ensure that all product contact surfaces are thoroughly cleaned to prevent cross-contamination (Annexure-7).
  5. Rinse all machine parts with water to remove any cleaning solution residue (Annexure-8).
  6. Allow the parts to air dry completely before reassembling the machine (Annexure-9).

5.3 Cleaning Validation

  1. QC must inspect the cleaned machine for any visible residues or contamination (Annexure-10).
  2. If any contamination is found, repeat the cleaning process and inspect again (Annexure-11).
  3. Once the inspection confirms that the machine is clean, document the results in the cleaning log (Annexure-12).

5.4 Final Reassembly and Start-Up

  1. Reassemble the packing machine once the parts have dried and are free from contaminants (Annexure-13).
  2. Run the machine empty for a short period to ensure everything is functioning properly and that no residual cleaning agents are left behind (Annexure-14).
  3. After the test run, check for any issues such as improper sealing or uneven product placement, and resolve them before starting production (Annexure-15).

5.5 Documentation and Record-Keeping

  1. Document each cleaning process, including the machine name, date, cleaning personnel, and inspection results (Annexure-16).
  2. Maintain cleaning logs for the required retention period according to company policies (Annexure-17).

6. Abbreviations

7. Documents

  1. Cleaning Log (Annexure-1)
  2. Cleaning Instructions (Annexure-2)
  3. Cleaning Solution Preparation Record (Annexure-3)
  4. External Surface Cleaning Log (Annexure-4)
  5. Machine Disassembly Log (Annexure-5)
  6. Internal Cleaning Log (Annexure-6)
  7. Product Contact Surface Cleaning Log (Annexure-7)
  8. Rinsing Record (Annexure-8)
  9. Drying Log (Annexure-9)
  10. Machine Inspection Log (Annexure-10)
  11. Re-cleaning Report (Annexure-11)
  12. Cleaning Validation Log (Annexure-12)
  13. Machine Reassembly Log (Annexure-13)
  14. Test Run Report (Annexure-14)
  15. Final Inspection Report (Annexure-15)
  16. Cleaning Documentation Log (Annexure-16)
  17. Cleaning Records Retention Log (Annexure-17)

8. References

9. SOP Version

Version: 2.0

10. Approval Section

Prepared By Checked By Approved By
Signature
Date
Name
Designation
Department

11. Annexures

Annexure-1: Cleaning Log

Machine Cleaning Date Operator Cleaning Status
Strip Packing Machine 01/07/2026 John Doe Completed

Annexure-2: Cleaning Instructions

Machine Instructions
Strip Packing Machine Follow manufacturer’s cleaning procedure, use compatible cleaning solution.

Annexure-3: Cleaning Solution Preparation Record

Solution Type Preparation Date Prepared By Concentration Used For
Alkaline Cleaner 01/07/2026 John Doe 5% solution External surface cleaning
Acidic Cleaner 01/07/2026 Jane Smith 2% solution Internal surface cleaning

Annexure-4: External Surface Cleaning Log

Machine Cleaning Date Operator Cleaning Method Cleaning Status
Strip Packing Machine 01/07/2026 John Doe Manual wipe down with cleaning solution Completed

Annexure-5: Machine Disassembly Log

Machine Disassembly Date Disassembled By Parts Disassembled Disassembly Status
Strip Packing Machine 01/07/2026 Jane Smith Hopper, Sealing Mechanism, Conveyor Completed

Annexure-6: Internal Cleaning Log

Machine Cleaning Date Operator Cleaning Solution Used Cleaning Method Cleaning Status
Strip Packing Machine 01/07/2026 John Doe Alkaline Cleaner Scrubbed with brush and soaked for 15 minutes Completed

Annexure-7: Product Contact Surface Cleaning Log

Machine Cleaning Date Operator Surface Area Cleaning Solution Used Cleaning Status
Strip Packing Machine 01/07/2026 Jane Smith Sealing Mechanism Acidic Cleaner Completed

Annexure-8: Rinsing Record

Machine Rinsing Date Rinsing Agent Operator Rinsing Status
Strip Packing Machine 01/07/2026 Water John Doe Completed

Annexure-9: Drying Log

Machine Drying Date Drying Method Operator Drying Status
Strip Packing Machine 01/07/2026 Air Drying Jane Smith Completed

Annexure-10: Machine Inspection Log

Machine Inspection Date Inspector Inspection Result Corrective Action (if any)
Strip Packing Machine 01/07/2026 John Doe Pass None

Annexure-11: Re-cleaning Report

Issue Re-cleaning Date Action Taken Responsible Person
Residue found after initial cleaning 02/07/2026 Re-cleaned and re-verified John Doe

Annexure-12: Cleaning Validation Log

Machine Validation Date Validation Method Validator Validation Status
Strip Packing Machine 01/07/2026 Visual Inspection and Sampling Jane Smith Pass

Annexure-13: Machine Reassembly Log

Machine Reassembly Date Reassembled By Reassembly Status
Strip Packing Machine 01/07/2026 John Doe Completed

Annexure-14: Test Run Report

Machine Test Run Date Tested By Test Run Result Comments
Strip Packing Machine 01/07/2026 Jane Smith Pass No issues observed

Annexure-15: Final Inspection Report

Machine Inspection Date Inspector Final Status Comments
Strip Packing Machine 01/07/2026 John Doe Pass All checks completed successfully
Exit mobile version