Sterile Injectable Manufacturing: SOP for Setup of Automatic Syringe Filling Systems – V 2.0

Sterile Injectable Manufacturing: SOP for Setup of Automatic Syringe Filling Systems – V 2.0

Standard Operating Procedure for Setup of Automatic Syringe Filling Systems


Department Sterile Injectable Manufacturing
SOP No. SOP/SIM/149/2025
Supersedes SOP/SIM/149/2022
Page No. Page 1 of 14
Issue Date 24/06/2025
Effective Date 26/06/2025
Review Date 24/06/2026

1. Purpose

This SOP establishes the procedure for setting up automatic syringe filling systems, ensuring that all mechanical, electronic, and control components are properly configured and verified prior to sterile batch production.

2. Scope

This SOP is applicable to

all prefilled syringe filling machines equipped with automation systems located in the sterile injectable manufacturing facility. It includes machine preparation, software checks, calibration, and line clearance procedures.

3. Responsibilities

  • Filling Machine Operator: Responsible for mechanical setup and basic parameter entry.
  • Automation Engineer: Oversees control system initialization, calibration, and troubleshooting.
  • QA Executive: Verifies setup and ensures readiness for GMP operations.

4. Accountability

The Production Manager and Head QA are accountable for proper execution of this SOP, adherence to GMP, and documentation accuracy.

5. Procedure

5.1 Pre-Setup Requirements

  1. Verify machine is clean and free of previous product residues (refer SOP/SIM/056/2025).
  2. Ensure all tools, parts, and fixtures required for setup are available.
  3. Check for availability of batch manufacturing records and prefilled syringe components.

5.2 Machine Setup

  1. Switch on the main power and initialize the PLC and HMI system.
  2. Load appropriate filling nozzles and syringe holders as per the syringe size (1 mL, 2.5 mL, etc.).
  3. Secure the transfer and conveyor belts using locking pins.
  4. Verify that clean-in-place (CIP) and sterilize-in-place (SIP) procedures have been completed.
  5. Confirm line clearance using Line Clearance Checklist (Annexure-1).

5.3 Parameter Configuration

  1. Input product-specific parameters including fill volume, speed, plunger stroke length, and backpressure.
  2. Verify input values with Master Formula Record (MFR).
  3. Activate servo control and validate motor synchronization between filling station and stoppering units.

5.4 Sensor and Camera Check

  1. Ensure syringe detection sensors are functional by placing test syringes.
  2. Test fill-no-syringe and overfill reject logic.
  3. Calibrate vision systems for plunger depth and fill level verification.

5.5 Dry Run Validation

  1. Conduct a 10-cycle dry run using dummy syringes with water-for-injection (WFI).
  2. Inspect movement precision, fill accuracy, and reject path activation.
  3. Record results in Dry Run Report (Annexure-2).

5.6 Verification and QA Approval

  1. Submit setup logs, dry run results, and MFR reference to QA.
  2. QA to verify batch number tagging, label setup, and safety interlocks.
  3. QA signs off the Setup Verification Form (Annexure-3).

5.7 Troubleshooting and Alarms

  1. In case of deviation in servo speed, verify gear ratios and encoder feedback.
  2. For camera errors, clean lens with IPA and reset software interface.
  3. Document errors and resolutions in Annexure-4: Machine Troubleshooting Log.

6. Abbreviations

  • SOP: Standard Operating Procedure
  • PLC: Programmable Logic Controller
  • HMI: Human Machine Interface
  • QA: Quality Assurance
  • MFR: Master Formula Record

7. Documents

  • Annexure-1: Line Clearance Checklist
  • Annexure-2: Dry Run Report
  • Annexure-3: Setup Verification Form
  • Annexure-4: Machine Troubleshooting Log

8. References

  • EU GMP Annex 1 – Manufacture of Sterile Medicinal Products
  • ISO 13408 – Aseptic Processing of Health Care Products

9. SOP Version

Version: 2.0

10. Approval Section

Prepared By Checked By Approved By
Signature
Date
Name
Designation Machine Operator QA Executive Head QA
Department Production Quality Assurance Quality Assurance

11. Annexures

Annexure-1: Line Clearance Checklist

Area Cleared (Yes/No) Remarks Checked By
Infeed Conveyor Yes Clean Sunil Rathi

Annexure-2: Dry Run Report

Cycle No. Fill Accuracy (%) Plunger Position Operator
1 98.7 Correct Ravi Yadav

Annexure-3: Setup Verification Form

Batch No. Machine ID QA Review Status Reviewed By
BN-2456 SYR-FILL-01 Approved Neha Kapoor

Annexure-4: Machine Troubleshooting Log

Date Issue Root Cause Action Taken Engineer
23/06/2025 Servo Jitter Encoder Cable Loose Reconnected and Tested Mohit Verma

Revision History

Revision Date Version Description Reason Approved By
01/01/2022 1.0 Initial SOP Release New Equipment QA Head
24/06/2025 2.0 Added Vision System and Annexures Annual Review QA Head