1. Purpose
To define the procedure for the operation of autoclaves used for sterilizing materials and equipment in the sterile injectable manufacturing facility. This ensures the maintenance of sterility, product quality, and compliance with GMP standards.
2.
Scope
This SOP applies to all autoclave operations conducted for sterilizing glassware, garments, equipment, and components used in the production of sterile injectable products.
3. Responsibilities
- Autoclave Operator: Performs pre-checks, loading, cycle execution, unloading, and documentation.
- Production Supervisor: Ensures readiness of materials and verifies the cycle parameters.
- QA Officer: Monitors sterilization records and ensures compliance with validated cycles.
4. Accountability
The Head of Production is accountable for ensuring that autoclaves are operated by trained personnel using approved and validated cycles.
5. Procedure
5.1 Pre-Operation Checklist
- Ensure autoclave is labeled as “CLEANED” and free from previous load remnants.
- Check integrity of door gaskets, chamber walls, and safety valves.
- Verify availability of utilities like steam, water, and compressed air.
- Record pre-use inspection in Autoclave Pre-Use Checklist (Annexure-1).
5.2 Loading the Autoclave
- Wear sterile garments before loading.
- Place items to be sterilized (e.g., vials, rubber stoppers, glassware) on perforated trays with proper spacing.
- Do not overload or block steam circulation pathways.
- Use sterilization indicators (Bowie-Dick or chemical) in each load.
5.3 Cycle Selection and Operation
- Select validated sterilization cycle on PLC/HMI panel based on material type.
- Typical parameters for porous load: 121°C for 30 minutes at 15 psi.
- Start the cycle and monitor the chamber pressure, temperature, and time.
- Record cycle start time, load details, and operator ID in the Sterilization Log (Annexure-2).
5.4 Monitoring During Sterilization
- Check real-time graph trends on the HMI screen for temperature and pressure consistency.
- Ensure no alarms or deviations occur. If triggered, abort and inform QA.
5.5 Unloading Post-Sterilization
- Allow chamber pressure to normalize before opening the door.
- Verify indicator color change or result to confirm sterilization efficacy.
- Unload items using sterile gloves and place them on sterile transfer trolleys.
- Complete unloading details in the record.
5.6 Post-Operation Cleaning
- Wipe the autoclave interior with 70% IPA.
- Drain condensate and log cleaning in Cleaning Record (Annexure-3).
6. Abbreviations
- SOP: Standard Operating Procedure
- HMI: Human Machine Interface
- QA: Quality Assurance
- IPA: Isopropyl Alcohol
- PLC: Programmable Logic Controller
7. Documents
- Autoclave Pre-Use Checklist – Annexure-1
- Sterilization Cycle Log – Annexure-2
- Cleaning Record of Autoclave – Annexure-3
8. References
- EU GMP Annex 1 – Manufacture of Sterile Medicinal Products
- WHO TRS 961 – Technical Report on Sterile Manufacturing
- ICH Q9 – Quality Risk Management
9. SOP Version
Version: 2.0
10. Approval Section
|
Prepared By |
Checked By |
Approved By |
| Signature |
|
|
|
| Date |
|
|
|
| Name |
|
|
|
| Designation |
Manufacturing Executive |
QA Executive |
Head QA |
| Department |
Production |
Quality Assurance |
Quality Assurance |
11. Annexures
Annexure-1: Autoclave Pre-Use Checklist
| Date |
Autoclave ID |
Gasket OK |
Steam Available |
Checked By |
| 18/06/2025 |
ACV-01 |
Yes |
Yes |
Rajesh Kumar |
Annexure-2: Sterilization Cycle Log
| Batch No. |
Cycle ID |
Start Time |
End Time |
Operator |
| STL/INJ/2025/034 |
ACV-121-30 |
09:00 |
10:00 |
Sunita Reddy |
Annexure-3: Cleaning Record of Autoclave
| Date |
Cleaned By |
Method Used |
Remarks |
| 18/06/2025 |
Ajay Verma |
70% IPA Wipe |
Completed |
Revision History
| Revision Date |
Revision No. |
Details |
Reason |
Approved By |
| 01/03/2022 |
1.0 |
Initial SOP Issue |
New Process |
QA Head |
| 18/06/2025 |
2.0 |
Updated with validation references and annexures |
Annual Review |
QA Head |