Skip to content
  • Clinical Studies
  • Pharma GMP
  • Pharma Tips
  • Stability Studies
  • Pharma Books
  • Schedule M

SOP Guide for Pharma

The Ultimate Resource for Pharmaceutical SOPs and Best Practices

  • Home
  • Job Safety Analysis (JSA)
    • Oral Dosage Forms (Tablets & Capsules)
    • Oral Liquid Dosage Forms (Syrups, Elixirs, Suspensions, Emulsions)
    • Powder and Granule Dosage Forms
    • Topical Dosage Forms (Creams, Ointments, Gels, Lotions, Pastes)
    • Transdermal Dosage Forms (Patches)
  • Standard Test Procedures (STP)
  • SOP – Blog Post
  • Toggle search form

SOP for IQ/OQ/PQ of Homogenizers for Creams and Ointments

Posted on By

SOP for IQ/OQ/PQ of Homogenizers for Creams and Ointments

Standard Operating Procedure for IQ/OQ/PQ of Homogenizers for Creams and Ointments

1) Purpose

The purpose of this Standard Operating Procedure (SOP) is to define the process for Installation Qualification (IQ), Operational Qualification (OQ), and Performance Qualification (PQ) of homogenizers used in the manufacturing of creams and ointments. This SOP ensures that homogenizers are correctly installed, operate according to specifications, and perform effectively under typical production conditions. The qualification process ensures that the homogenizer produces uniform emulsions with the required consistency, particle size distribution, and stability, meeting the necessary regulatory and quality standards.

2) Scope

This SOP applies to the qualification of homogenizers used for the preparation of creams, ointments, emulsions, and other semi-solid pharmaceutical formulations. The qualification process includes IQ, OQ, and PQ stages to verify that the homogenizer operates as intended and produces products within specified quality parameters. This SOP is applicable to both new homogenizers and those that have undergone repairs, upgrades, or relocations. The qualification ensures that the equipment meets all required regulatory standards and produces consistent, high-quality products.

3) Responsibilities

Operators: Responsible for assisting in the IQ, OQ, and PQ processes, ensuring that the homogenizer is operated according to the qualification protocols

and that critical parameters are monitored during testing.
Quality Assurance (QA): Ensures that the IQ, OQ, and PQ of the homogenizer are carried out in compliance with this SOP and meet all regulatory requirements. QA is also responsible for reviewing and approving all qualification reports and documentation.
Production Supervisors: Oversee the qualification processes to ensure that operators follow the protocol and that the homogenizer operates within the specified parameters.
Validation Team: Responsible for developing the qualification protocols, executing the IQ, OQ, and PQ runs, and analyzing the results to ensure the homogenizer meets all performance criteria.
Maintenance Personnel: Ensures that the homogenizer is properly installed, maintained, and calibrated, and that all mechanical and electrical systems are functioning correctly during the qualification process.

See also  SOP for Qualification of Syrup Manufacturing Tanks

4) Procedure

The following steps should be followed for the IQ, OQ, and PQ of homogenizers used for creams and ointments:

1. Installation Qualification (IQ):
1.1 Review equipment specifications and manufacturer manuals to ensure that the homogenizer meets the necessary requirements for installation.
1.2 Verify that all required utilities (e.g., electrical power, compressed air, water, cooling systems) are available and meet the specifications required for proper operation.
1.3 Ensure that the installation site meets the required environmental conditions such as temperature, humidity, cleanliness, and space.
1.4 Confirm that all mechanical components are correctly installed, including the rotor-stator assembly, motor, cooling jackets, and liquid handling systems.
1.5 Ensure that all electrical components, including sensors, control systems, and alarms, are properly connected and functioning.
1.6 Perform a visual inspection to confirm that the equipment is installed according to the manufacturer’s instructions and that all components are intact.
1.7 Complete the IQ documentation, including checklists, equipment manuals, and relevant installation records, ensuring that all information is recorded and signed off by responsible personnel.

2. Operational Qualification (OQ):
2.1 Verify that all operational controls, such as homogenization speed, pressure, and temperature, are properly set and calibrated.
2.2 Conduct a dry run of the homogenizer to verify that it operates without issues. Monitor key parameters such as motor performance, cooling system operation, and uniformity of mixing.
2.3 Test all control systems, ensuring that the start/stop, speed controls, pressure adjustments, and emergency stop functions work correctly.
2.4 Inspect the homogenizing process to ensure that the mixture is being emulsified efficiently and that the particle size distribution is within acceptable limits.
2.5 Verify that the cooling system functions correctly to prevent overheating of the product during homogenization.
2.6 Document the results of the OQ, noting any deviations or issues encountered and corrective actions taken.

See also  SOP for Process Validation of Lyophilized Products

3. Performance Qualification (PQ):
3.1 Conduct the homogenization process using a product or simulated product (e.g., inert solution) to monitor performance under typical production conditions.
3.2 Measure the particle size distribution of the emulsified product to ensure that it meets predefined specifications for uniformity and consistency.
3.3 Verify that the homogenizer operates at the required throughput without affecting the quality of the emulsion.
3.4 Perform a visual inspection to ensure that the final product has the required consistency and is free of large particles or visible defects.
3.5 Measure the temperature of the product during homogenization to ensure that the product is not overheated and remains within temperature-sensitive limits.
3.6 Document the results of the PQ, including particle size data, temperature profiles, throughput, and any process deviations. Ensure that all records are signed and reviewed by responsible personnel.

4. Documentation and Reporting:
4.1 Record all data during the IQ, OQ, and PQ processes, including batch records, equipment logs, process parameters, and inspection results for particle size distribution, throughput, and temperature.
4.2 Ensure that all forms, reports, and certificates are completed and signed by responsible personnel.
4.3 Perform statistical analysis on the collected data to assess the consistency and reliability of the homogenization process. This analysis should confirm that the homogenizer operates consistently within predefined parameters and meets the acceptance criteria.
4.4 Prepare a final qualification report, summarizing the results of the IQ, OQ, and PQ, including any deviations, corrective actions, and conclusions regarding the homogenizer’s performance.

See also  SOP for Qualification of Sterilizers (Autoclaves)

5. Requalification:
5.1 Requalify the homogenizer if significant changes are made to the equipment, such as replacing major components, relocating the machine, or modifying the homogenizing system.
5.2 Periodically perform requalification to ensure that the equipment continues to perform as expected and remains in compliance with regulatory requirements.

5) Abbreviations

  • IQ: Installation Qualification
  • OQ: Operational Qualification
  • PQ: Performance Qualification
  • QA: Quality Assurance
  • SOP: Standard Operating Procedure

6) Documents

  • IQ/OQ/PQ Protocol
  • Equipment Manufacturer Specifications
  • Installation and Setup Reports
  • Calibration Records
  • Homogenization Process Records
  • Particle Size Distribution Logs
  • Deviation and Corrective Action Reports

7) Reference

  • FDA Guidance for Industry: Equipment Qualification
  • International Council for Harmonisation (ICH) Q7: Good Manufacturing Practice Guide for Active Pharmaceutical Ingredients
  • ISO 9001: Quality Management Systems – Requirements
  • USP Chapter 1151: Pharmaceutical Dosage Forms

8) SOP Version

Version 1.0 – Effective Date: DD/MM/YYYY

Annexure

Template 1: IQ/OQ/PQ Test Record

Date Time Operator Initials Test Type (IQ/OQ/PQ) Test Results Comments
DD/MM/YYYY HH:MM Operator Name IQ/OQ/PQ Pass/Fail Comments
           

Template 2: Particle Size Distribution Log

Batch No. Test Date Particle Size (µm) Uniformity (Pass/Fail) Operator Initials
Batch Number DD/MM/YYYY Particle Size Pass/Fail Operator Name
         

Template 3: Homogenizer Calibration and Maintenance Log

Equipment Name Calibration Date Maintenance Performed Next Calibration Date Operator Initials
Homogenizer Model DD/MM/YYYY Maintenance Tasks DD/MM/YYYY Operator Name
         
Validations and Qualifications Tags:Cleaning Validation in Pharmaceutical Industry, Computer System Validation in Pharma, Computer System Validation in Pharmaceuticals, Define Validation in Pharma, Equipment Qualification in Pharma, Method Validation in Pharma, Performance Qualification in Pharma, Pharma Validation, Pharmaceutical Cleaning Validation, Pharmaceutical Method Validation, Pharmaceutical Process Validation, Pharmaceutical Process Validation SOP, Pharmaceutical Validation Definition, Pharmaceutical Validation Services, Process Validation Definition in Pharma, Process Validation in Pharma, Process Validation in Pharma Industry, Process Validation in Pharmaceutical Industry, Prospective Validation in Pharma, Qualification in Pharma, Software Validation in Pharmaceutical Industry, SOP for Analytical Method Validations, SOP for Cleaning Validations, SOP for Equipment Validations, SOP for Process Validation, SOP for Validations, Types of Validation in Pharma, Types of Validation in Pharmaceutical Industry, Validation in Pharmaceutical Industry, Validation Life Cycle in Pharma

Post navigation

Previous Post: SOP for Handling of High-Throughput Screening (HTS) Equipment
Next Post: SOP for Qualification of Mixing Tanks with Agitators

Standard Operating Procedures V 1.0

  • Aerosols
  • Analytical Method Development
  • Bioequivalence Bioavailability Study
  • Capsule Formulation
  • Clinical Studies
  • Creams
  • Data Integrity
  • Dental Dosage Forms
  • Drug Discovery
  • Environment, Health and Safety
  • Formulation Development
  • Gels
  • Good Distribution Practice
  • Good Warehousing Practices
  • In-Process Control
  • Injectables
  • Liquid Orals
  • Liposome and Emulsion Formulations
  • Lotions
  • Lyophilized Products
  • Maintenance Dept.
  • Medical Devices
  • Metered-Dose Inhaler
  • Microbiology Testing
  • Nanoparticle Formulation
  • Nasal Spray Formulations
  • Nebulizers
  • Ocular (Eye) Dosage Forms
  • Ointments
  • Otic (Ear) Dosage Forms
  • Pharmacovigilance
  • Powder & Granules
  • Purchase Departments
  • Quality Assurance
  • Quality Control
  • Raw Material Stores
  • Regulatory Affairs
  • Tablet Manufacturing
  • Rectal Dosage Forms
  • Transdermal Patches
  • Vaginal Dosage Forms
  • Validations and Qualifications

Read SOPs in your Language:

 - 
Bengali
 - 
bn
English
 - 
en
Gujarati
 - 
gu
Hindi
 - 
hi
Malayalam
 - 
ml
Marathi
 - 
mr
Punjabi
 - 
pa
Tamil
 - 
ta
Telugu
 - 
te

NEW! Revised SOPs – V 2.0

  • Aerosols V 2.0
  • Analytical Method Development V 2.0
  • API Manufacturing V 2.0
  • BA-BE Studies V 2.0
  • Biosimilars V 2.0
  • Capsules V 2.0
  • Creams V 2.0
  • Elixers V 2.0
  • Ointments V 2.0
  • Raw Material Warehouse V 2.0
  • Tablet Manufacturing V2.0

New Publication: A must for All.

Copyright © 2025 SOP Guide for Pharma.

Powered by PressBook WordPress theme

Go to mobile version