SOP Guide for Pharma

SOP for Cross-Checking Weighed Materials Before Issuance – V 2.0

SOP for Cross-Checking Weighed Materials Before Issuance – V 2.0

Standard Operating Procedure for Cross-Checking Weighed Materials Before Issuance

Department Warehouse / Production / Quality Assurance
SOP No. SOP/RM/199/2025
Supersedes SOP/RM/199/2022
Page No. Page 1 of 15
Issue Date 04/05/2025
Effective Date 11/05/2025
Review Date 04/05/2026

1. Purpose

This Standard Operating Procedure (SOP) outlines the process for cross-checking weighed raw materials before issuance to ensure accuracy, traceability, and compliance with Good Manufacturing Practices (GMP).

2. Scope

This SOP applies to all warehouse, production, and quality assurance personnel involved in the weighing, verification, and issuance of raw materials for pharmaceutical manufacturing.

3. Responsibilities

  • Warehouse Staff: Weigh raw materials accurately and ensure proper documentation.
  • Production Supervisor: Cross-check and verify the weighed materials before usage in production.
  • Quality Assurance (QA) Team: Oversee compliance with weighing protocols and conduct periodic audits.

4. Accountability

The Warehouse Manager is accountable for ensuring accurate weighing and cross-checking of materials before issuance. The Production Supervisor is responsible for verifying the correctness of materials used in manufacturing, while the QA Manager ensures compliance through audits.

5. Procedure

5.1 Preparation for Material Weighing

  1. Review of Batch Manufacturing Record (BMR):
    • The Warehouse Supervisor reviews the BMR to
identify the required materials and quantities.
  • Document the review in the BMR Review Log (Annexure-1).
  • Calibration of Weighing Equipment:
    • Ensure that all weighing equipment is calibrated before use.
    • Record calibration details in the Equipment Calibration Log (Annexure-2).
  • 5.2 Material Weighing Process

    1. Weighing of Materials:
      • Weigh the materials according to the specified quantity in the BMR using calibrated equipment.
      • Document the weighed quantities in the Material Weighing Log (Annexure-3).
    2. Labeling of Weighed Materials:
      • Label each weighed container with the material name, batch number, and weight.
      • Record labeling details in the Material Labeling Log (Annexure-4).

    5.3 Cross-Checking of Weighed Materials

    1. Verification of Weighed Materials:
      • The Production Supervisor or QA personnel cross-check the weighed materials against the BMR for accuracy.
      • Document the verification in the Material Verification Log (Annexure-5).
    2. Documentation of Discrepancies:
      • Any discrepancies between the weighed materials and the BMR should be reported to QA immediately.
      • Document discrepancies in the Discrepancy Log (Annexure-6).

    5.4 Issuance of Verified Materials

    1. Approval for Issuance:
      • Only materials that have been cross-checked and verified should be issued to the production department.
      • Document the issuance in the Material Issuance Log (Annexure-7).
    2. Handling of Non-Compliant Materials:
      • Non-compliant materials should be quarantined and corrective actions should be initiated.
      • Document corrective actions in the Corrective Action Log (Annexure-8).

    5.5 Training and Compliance Monitoring

    1. Training on Weighing and Cross-Checking Procedures:
      • Conduct regular training sessions for warehouse and production staff on weighing and cross-checking procedures.
      • Document training sessions in the Training Log (Annexure-9).
    2. Compliance Audits:
      • QA personnel conduct periodic audits to ensure compliance with weighing and cross-checking procedures.
      • Record audit findings in the Compliance Audit Log (Annexure-9).

    6. Abbreviations

    • SOP: Standard Operating Procedure
    • BMR: Batch Manufacturing Record
    • QA: Quality Assurance
    • GMP: Good Manufacturing Practices

    7. Documents

    1. BMR Review Log (Annexure-1)
    2. Equipment Calibration Log (Annexure-2)
    3. Material Weighing Log (Annexure-3)
    4. Material Labeling Log (Annexure-4)
    5. Material Verification Log (Annexure-5)
    6. Discrepancy Log (Annexure-6)
    7. Material Issuance Log (Annexure-7)
    8. Corrective Action Log (Annexure-8)
    9. Training Log (Annexure-9)

    8. References

    • 21 CFR Part 211 – Current Good Manufacturing Practice for Finished Pharmaceuticals
    • WHO Guidelines on GMP for Pharmaceutical Products
    • FDA Guidance on Weighing and Verification Procedures

    9. SOP Version

    Version: 2.0

    10. Approval Section

    Prepared By Checked By Approved By
    Signature
    Date
    Name
    Designation
    Department

    Annexure-1: BMR Review Log

    Date BMR Number Reviewed By Remarks
    04/05/2025 BMR-12345 Ravi Kumar Reviewed and Approved

    Annexure-2: Equipment Calibration Log

    Date Equipment ID Calibration Status Calibrated By
    04/05/2025 WEIGH-001 Calibrated Neha Verma

    Annexure-3: Material Weighing Log

    Date Material Name Batch Number Weighed Quantity (kg) Weighed By
    04/05/2025 Ibuprofen API BN-67890 25 kg Kiran Patel

    Annexure-4: Material Labeling Log

    Date Material Name Label Information Labeled By
    04/05/2025 Ibuprofen API Batch BN-67890, 25 kg Amit Joshi

    Annexure-5: Material Verification Log

    Date Material Name Batch Number Verified By
    04/05/2025 Ibuprofen API BN-67890 QA Team

    Annexure-6: Discrepancy Log

    Date Discrepancy Identified Description Reported By
    04/05/2025 Weight Mismatch Weighed quantity did not match BMR QA Team

    Annexure-7: Material Issuance Log

    Date Material Name Batch Number Issued To
    04/05/2025 Ibuprofen API BN-67890 Production Department

    Annexure-8: Corrective Action Log

    Date Issue Corrective Action Taken Performed By
    04/05/2025 Weight Mismatch Reweighed and corrected the quantity Warehouse Staff

    Annexure-9: Training Log

    Date Employee Name Training Topic Trainer Remarks
    04/05/2025 Neha Verma Weighing and Cross-Checking Procedures QA Manager Completed Successfully

    Revision History:

    Revision Date Revision No. Revision Details Reason for Revision Approved By
    01/01/2024 1.0 Initial Version New SOP Implementation QA Head
    04/05/2025 2.0 Added procedures for cross-checking weighed materials. Regulatory Update QA Head
    Exit mobile version