SOP Guide for Pharma

Ointments: SOP for Conducting Preventive Maintenance on Validated Equipment – V 2.0

SOP for Conducting Preventive Maintenance on Validated Equipment – V 2.0

Procedure for Conducting Preventive Maintenance on Validated Equipment

Department Engineering/Quality Assurance (QA)/Validation/Production
SOP No. SOP/Ointment/140
Supersedes V 1.0
Page No. Page X of Y
Issue Date [Insert Issue Date]
Effective Date [Insert Effective Date]
Review Date [Insert Review Date]

1. Purpose

The purpose of this Standard Operating Procedure (SOP) is to define the process for conducting preventive maintenance on validated equipment used in ointment manufacturing. Proper maintenance ensures continued operational efficiency, reliability, and compliance with regulatory standards.

2. Scope

This SOP applies to all personnel in the Engineering, Quality Assurance (QA), Validation, and Production departments responsible for scheduling, performing, and documenting preventive maintenance activities.

3. Responsibilities

  • Engineering Team: Performs scheduled maintenance and repairs.
  • QA Officer: Ensures maintenance activities comply with validation requirements.
  • Validation Team: Verifies that maintenance does not impact validation status.
  • Production Supervisor: Coordinates maintenance schedules with production plans.
  • QA Manager: Approves maintenance records and ensures compliance with GMP guidelines.

4. Accountability

The Engineering and QA Managers are accountable for ensuring that preventive maintenance is conducted as per GMP, FDA, ICH, and WHO guidelines.

5. Procedure

5.1 Identification of Equipment for Preventive Maintenance

  • Maintain a master list of validated equipment requiring preventive maintenance.
  • Classify equipment based on criticality:
    • High-Criticality: Mixing tanks, filling machines, HVAC systems.
    • Medium-Criticality: Compressors, vacuum pumps, sealing machines.
    • Low-Criticality: Storage racks, conveyors, labeling machines.

5.2 Preventive Maintenance Scheduling

  • Develop a Preventive
Maintenance (PM) schedule based on:
  • Manufacturer recommendations
  • Equipment usage frequency
  • Historical performance data
  • Ensure PM activities do not disrupt ongoing production.
  • Assign trained personnel for maintenance execution.
  • 5.3 Preventive Maintenance Execution

    • Ensure the equipment is powered down and secured before maintenance.
    • Use only approved tools, lubricants, and spare parts.
    • Perform maintenance tasks including:
      • Lubrication of moving parts
      • Inspection and replacement of worn-out components
      • Cleaning and removal of debris
      • Calibration of critical sensors and instruments
    • Record all activities in the Preventive Maintenance Log.

    5.4 Post-Maintenance Validation Check

    • QA must verify that maintenance activities did not impact validated parameters.
    • Perform a test run to ensure proper functionality.
    • Monitor equipment performance for at least one production batch.

    5.5 Handling Deviations

    • If issues are identified post-maintenance:
      • Document deviation details in the Deviation Report.
      • Investigate the root cause and implement corrective actions.
      • Perform requalification of the affected equipment.

    5.6 Documentation and Review

    • Maintain maintenance logs, calibration records, and spare parts usage records.
    • QA must review and approve all maintenance reports.
    • Ensure documentation is available for regulatory audits.

    6. Abbreviations

    • GMP – Good Manufacturing Practices
    • QA – Quality Assurance
    • PM – Preventive Maintenance
    • HVAC – Heating, Ventilation, and Air Conditioning

    7. Documents

    • Preventive Maintenance Schedule (Annexure-1)
    • Preventive Maintenance Log (Annexure-2)

    8. References

    • ICH Q7 – Good Manufacturing Practice Guide
    • WHO Guidelines for Equipment Maintenance
    • US FDA Guidance on Preventive Maintenance

    9. SOP Version

    Version 2.0

    10. Approval Section

    Prepared By Checked By Approved By
    Signature
    Date
    Name
    Designation
    Department

    11. Annexures

    Annexure-1: Preventive Maintenance Schedule

    Equipment ID Equipment Type Frequency Next Maintenance Due Assigned Technician
    MIX-1001 Mixing Tank Quarterly 01/04/2025 John Doe
    FILL-2002 Filling Machine Monthly 15/02/2025 Jane Smith

    Annexure-2: Preventive Maintenance Log

    Date Equipment ID Maintenance Performed Parts Replaced Technician Reviewed By
    01/01/2025 MIX-1001 Lubrication, Sensor Calibration None John Doe QA Manager
    15/01/2025 FILL-2002 Seal Replacement, Belt Adjustment Sealing Gasket Jane Smith QA Manager

    12. Revision History:

    Revision Date Revision No. Details of Revision Reason for Revision Approved By
    01/01/2024 1.0 Initial Version New SOP QA Head
    01/02/2025 2.0 Updated SOP Format Standardization of Document QA Head
    Exit mobile version