SOP Guide for Pharma

Gel Manufacturing: SOP for Disinfection of Gel Manufacturing Area After Maintenance – V 2.0

Gel Manufacturing: SOP for Disinfection of Gel Manufacturing Area After Maintenance – V 2.0

Standard Operating Procedure for Disinfection of Gel Manufacturing Area After Maintenance

Department Gel Manufacturing
SOP No. SOP/GM/146/2025
Supersedes SOP/GM/146/2022
Page No. Page 1 of 11
Issue Date 09/06/2025
Effective Date 11/06/2025
Review Date 09/06/2027

1. Purpose

To establish a standard procedure for cleaning and disinfecting gel manufacturing areas after any maintenance activity, ensuring the area is free of contaminants and ready for production resumption.

2. Scope

This SOP applies to all classified rooms, equipment zones, and adjacent corridors in the gel manufacturing facility that undergo maintenance activities requiring entry by engineering or external personnel.

3. Responsibilities

  • Engineering Department: Notifies completion of maintenance and performs initial cleaning of their tools and work area.
  • Housekeeping Staff: Executes disinfection activities as per defined procedure.
  • Production Supervisor: Verifies completion
of disinfection and signs off clearance.
  • QA Executive: Performs final inspection and documents area release.
  • 4. Accountability

    The Head – Manufacturing is accountable for ensuring that post-maintenance disinfection is timely and effectively completed as per GMP standards.

    5. Procedure

    5.1 Preparation for Disinfection

    1. Engineering personnel must inform production upon completion of maintenance activity.
    2. All tools, debris, maintenance materials, and spare parts must be removed from the area.
    3. Coverings, temporary partitions, and tapes used during maintenance must be dismantled.

    5.2 Initial Dry Cleaning

    1. Remove visible dirt, dust, or particles using sterile dry mops or vacuum cleaners with HEPA filters.
    2. Wipe equipment surfaces using lint-free cleanroom wipes.

    5.3 Disinfection Steps

    1. Use freshly prepared 2.5% v/v Isopropyl Alcohol (IPA) solution or an approved disinfectant.
    2. Apply the disinfectant starting from top to bottom: walls, equipment surfaces, floors.
    3. Use separate mops for each surface to avoid cross-contamination.
    4. Ensure wet contact time of at least 10 minutes or as recommended by the disinfectant manufacturer.
    5. Use a 2-step method (cleaning followed by disinfection) in Grade B or Grade C areas.

    5.4 Post-Disinfection Verification

    1. Inspect the area for cleanliness, absence of residues, and intact surfaces.
    2. Check environmental parameters (temperature, humidity) if sensors were disturbed.
    3. Fill disinfection logbook with details of date, time, area cleaned, person responsible, and type of disinfectant used.

    5.5 Clearance for Use

    1. Production Supervisor inspects the area and signs the internal area clearance form.
    2. QA Executive performs a final walkthrough and signs off for area release.

    6. Abbreviations

    • IPA: Isopropyl Alcohol
    • GMP: Good Manufacturing Practice
    • QA: Quality Assurance

    7. Documents

    1. Disinfection Logbook – Annexure-1
    2. Area Clearance Form – Annexure-2
    3. Approved Disinfectant List – Annexure-3

    8. References

    • WHO TRS 961 Annex 6: GMP for Pharmaceutical Products
    • EU GMP Volume 4 Annex 1: Manufacture of Sterile Medicinal Products
    • FDA Guidance for Industry: Aseptic Processing

    9. SOP Version

    Version: 2.0

    10. Approval Section

    Prepared By Checked By Approved By
    Signature
    Date
    Name
    Designation Jr. Production Chemist QA Executive Head – Manufacturing
    Department Gel Manufacturing Quality Assurance Manufacturing

    11. Annexures

    Annexure-1: Disinfection Logbook

    Date Time Area Disinfectant Used Prepared By Signature

    Annexure-2: Area Clearance Form

    Area
    Maintenance Completed On
    Disinfection Done By
    Production Clearance ☐ Yes ☐ No
    QA Clearance ☐ Yes ☐ No
    Remarks

    Annexure-3: Approved Disinfectant List

    Disinfectant Name Concentration Contact Time Applicable Area

    Revision History

    Revision Date Revision No. Change Description Reason Approved By
    12/07/2022 1.0 Initial release New facility procedure QA Head
    09/06/2025 2.0 Updated to include Annexure for Area Clearance Annual SOP Review QA Head