Standard Operating Procedure for Use of Mixing Tanks with Variable Speed Agitators
Department | Elixir Department |
---|---|
SOP No. | SOP/ELX/056/2025 |
Supersedes | SOP/ELX/056/2022 |
Page No. | Page 1 of 8 |
Issue Date | 11/04/2025 |
Effective Date | 15/04/2025 |
Review Date | 11/04/2026 |
1. Purpose
To define the procedure for the safe and effective operation of mixing tanks equipped with variable speed agitators in the Elixir Department for ensuring homogeneous mixing of components.
2. Scope
This SOP is applicable to all mixing tanks with variable speed agitators used during the manufacturing of elixir formulations in the production area.
3. Responsibilities
- Machine Operator:
- Operate the agitator as per defined speed and time settings in the BMR.
- Inspect, clean, and maintain agitator components before and after use.
- Production Supervisor:
- Ensure proper functioning and calibration of variable speed controller.
- Verify process parameters and approve equipment for use.
- Engineering Department:
- Perform periodic preventive maintenance of the agitator system.
See also Elixir Department: SOP for Transfer of Materials to Quarantine Area Post Dispensing - V 2.0
4. Accountability
The Production Manager is accountable for ensuring the equipment is used safely and effectively and maintained in validated condition.
5. Procedure
5.1 Equipment Setup
- Check that the tank is clean and labeled “CLEANED” as per SOP/ELX/051/2025.
- Ensure agitator shaft, blade, seals, and electrical connections are intact and secure.
- Connect the variable speed control panel and verify the operational display.
5.2 Pre-Operational Checks
- Ensure the emergency stop button is functional.
- Verify tank and agitator identification numbers match the BMR.
- Check RPM calibration tag and verify the last maintenance status.
5.3 Agitator Operation
- Start the agitator at the lowest speed setting (e.g., 20–30 RPM) for initial mixing.
- Gradually increase to the desired speed range based on batch type (e.g., 60–150 RPM).
- Refer to BMR for target mixing speeds for specific stages (e.g., dissolution, dispersion).
- Use timer function, if available, to monitor mixing duration.
- Record actual speed, mixing time, and temperature (if applicable) in Mixing Log (Annexure-1).
5.4 During Operation
- Monitor the mixing visually for vortex formation, sedimentation, or splashing.
- Adjust speed gradually if change in viscosity or foaming is observed.
- If abnormal noise or vibrations occur, stop the agitator immediately and inform engineering.
5.5 Post-Operation
- Turn off the agitator and disconnect the power supply.
- Clean agitator shaft and blade thoroughly using purified water and approved detergent.
- Label the equipment as “TO BE CLEANED” or “CLEANED” with date and signature.
5.6 Maintenance and Calibration
- Ensure that the RPM controller is calibrated every 6 months by Engineering Department.
- Record calibration date and due date on the calibration tag (Annexure-2).
6. Abbreviations
- RPM: Revolutions Per Minute
- SOP: Standard Operating Procedure
- BMR: Batch Manufacturing Record
7. Documents
- Mixing Log (Annexure-1)
- RPM Calibration Log (Annexure-2)
- Equipment Cleaning Record (Annexure-3)
8. References
- WHO TRS 986 Annex 2 – GMP for Pharmaceutical Production
- 21 CFR 211.63 – Equipment Design, Size, and Location
9. SOP Version
Version: 2.0
10. Approval Section
Prepared By | Checked By | Approved By | |
---|---|---|---|
Signature | |||
Date | |||
Name | |||
Designation | |||
Department |
11. Annexures
Annexure-1: Mixing Log
Date | Batch No. | Tank ID | Start Time | End Time | RPM | Operator | Supervisor |
---|---|---|---|---|---|---|---|
11/04/2025 | ELX-1002 | MX-TNK-07 | 10:00 AM | 10:45 AM | 120 | Rajesh Kumar | Sunita Reddy |
Annexure-2: RPM Calibration Log
Date | Equipment ID | Calibrated RPM | Calibrated By | Next Due |
---|---|---|---|---|
01/03/2025 | MX-TNK-07 | 60–150 | Vikram Chauhan | 01/09/2025 |
Annexure-3: Equipment Cleaning Record
Date | Equipment ID | Cleaning Status | Cleaned By | Verified By |
---|---|---|---|---|
11/04/2025 | MX-TNK-07 | Cleaned | Ajay Desai | Manju Sharma |
Revision History:
Revision Date | Revision No. | Revision Details | Reason for Revision | Approved By |
---|---|---|---|---|
01/01/2024 | 1.0 | Initial Issue | New SOP | QA Head |
11/04/2025 | 2.0 | Included Preventive Maintenance and Calibration | Process Control Improvement | QA Head |