Standard Operating Procedure for Preventive Maintenance of Filling Machines in Elixir Manufacturing
| Department | Elixir Department |
|---|---|
| SOP No. | SOP/ELX/147/2025 |
| Supersedes | SOP/ELX/147/2022 |
| Page No. | Page 1 of 10 |
| Issue Date | 11/04/2025 |
| Effective Date | 15/04/2025 |
| Review Date | 11/04/2026 |
1. Purpose
To define the procedure for preventive maintenance (PM) of filling machines used in elixir manufacturing, ensuring consistent performance, minimizing downtime, and preventing batch contamination due to mechanical failure.
2. Scope
This SOP applies to all automatic, semi-automatic, and volumetric filling machines used for filling elixirs into containers in the Elixir Department.
3. Responsibilities
- Engineering Department:
- Perform preventive maintenance activities as per the schedule.
- Record all PM activities and calibrations in the Equipment Maintenance Log.
- Production Operator:
- Report any unusual machine behavior during operation.
- Ensure the machine is ready for maintenance (clean, shutdown, de-energized).
- QA Officer:
- Review PM records and verify completion before machine release for use.
4. Accountability
The Engineering Head is accountable for timely and compliant maintenance of filling machines. The Production Head is responsible for machine readiness and coordination.
5. Procedure
5.1 Preparation for Maintenance
- Verify that the filling machine is cleaned and labeled as “UNDER MAINTENANCE.”
- Switch off the main power supply and display “DO NOT OPERATE” tag.
- Ensure all compressed air, WFI, and vacuum lines are disconnected (if applicable).
5.2 Preventive Maintenance Checklist
- Inspect and clean nozzles, filling heads, and valve seats.
- Check alignment and integrity of pistons or dosing cylinders.
- Lubricate mechanical moving parts like cams, levers, and chains.
- Check electrical and PLC panels for dust accumulation and loose connections.
- Tighten all sensors and proximity switches.
- Inspect pneumatic lines and actuators for leaks or damage.
- Verify load cell calibration (if applicable).
5.3 Calibration and Test Run
- Perform volume calibration using certified volumetric flasks or standard weights.
- Run a dummy cycle with purified water and observe filling accuracy and speed.
- Record all calibration values and corrections made in the Calibration Log (Annexure-1).
5.4 Documentation and Handover
- Complete the Preventive Maintenance Checklist and record observations in the Maintenance Log (Annexure-2).
- QA to review PM records and authorize machine usage.
- Label the machine as “READY FOR USE” after QA clearance.
5.5 Maintenance Frequency
- Monthly: Basic mechanical inspection and lubrication.
- Quarterly: Detailed inspection with calibration verification.
- Annually: Complete overhaul and replacement of worn parts.
6. Abbreviations
- SOP: Standard Operating Procedure
- QA: Quality Assurance
- PM: Preventive Maintenance
- WFI: Water for Injection
- PLC: Programmable Logic Controller
7. Documents
- Calibration Log (Annexure-1)
- Preventive Maintenance Log (Annexure-2)
- QA Clearance Form
8. References
- 21 CFR Part 211 – Equipment Maintenance
- WHO TRS 986 – Maintenance and Calibration Guidelines
- ICH Q9 – Quality Risk Management
9. SOP Version
Version: 2.0
10. Approval Section
| Prepared By | Checked By | Approved By | |
|---|---|---|---|
| Signature | |||
| Date | |||
| Name | |||
| Designation | |||
| Department |
11. Annexures
Annexure-1: Calibration Log
| Date | Machine ID | Volume Set | Volume Delivered | Deviation | Status | Engineer |
|---|---|---|---|---|---|---|
| 11/04/2025 | FM-ELX-02 | 100 ml | 99.8 ml | -0.2 ml | Pass | Ramesh Patel |
Annexure-2: Preventive Maintenance Log
| Date | Machine ID | Activity Performed | Parts Lubricated | Replaced Components | Remarks | Engineer |
|---|---|---|---|---|---|---|
| 11/04/2025 | FM-ELX-02 | Quarterly PM | Chain, Piston Rods | O-ring | Performance OK | Ramesh Patel |
Revision History:
| Revision Date | Revision No. | Revision Details | Reason for Revision | Approved By |
|---|---|---|---|---|
| 01/01/2024 | 1.0 | Initial SOP Release | New SOP | QA Head |
| 11/04/2025 | 2.0 | Updated calibration and safety instructions | Compliance Update | QA Head |