SOP Guide for Pharma

Biosimilars: SOP for Temperature Control in Bioreactor Operations – V 2.0


Biosimilars: SOP for Temperature Control in Bioreactor Operations – V 2.0


Standard Operating Procedure for Temperature Control in Bioreactor Operations for Biosimilar Manufacturing

Department Biosimilars
SOP No. SOP/BS/068/2025
Supersedes SOP/BS/068/2022
Page No. Page 1 of 11
Issue Date 04/05/2025
Effective Date 06/05/2025
Review Date 04/05/2026

1. Purpose

To define the procedure for controlling, monitoring, and documenting temperature parameters in bioreactors used for upstream biosimilar manufacturing to ensure optimal cell culture conditions and regulatory compliance.

2. Scope

This SOP applies to all stainless steel and single-use bioreactors (1L to 2000L capacity) operated in the upstream process areas for biosimilar production at [Insert Facility Name].

3. Responsibilities

4. Accountability

The Head of Bioprocess Operations is accountable for ensuring adherence to temperature control procedures and reporting any deviations or equipment malfunctions.

5. Procedure

5.1 Pre-Operation Verification

  1. Ensure bioreactor temperature sensor is calibrated within the last 6 months (Annexure-1).
  2. Verify setpoint and deadband settings as per batch record: typically 36.5°C–37.5°C.
  3. Confirm that the control unit (PID controller or PLC) is operational and shows no prior faults.

5.2 Temperature Setpoint Configuration

  1. Set temperature on the bioreactor control panel as per process requirement (e.g., 37.0°C).
  2. Input control parameters (P, I, D values) based on system tuning documentation.
  3. Start temperature control loop, allowing jacket fluid to circulate.

5.3 Monitoring During Operation

  1. Monitor bioreactor display panel for live temperature and jacket temperature every 2 hours.
  2. Record actual temperature in the Bioreactor Monitoring Log (Annexure-2).
  3. If deviation > ±0.5°C from setpoint, initiate deviation handling (SOP/BS/050/2025).

5.4 Alarm Response and Troubleshooting

  1. In case of temperature alarm:
    • Verify probe immersion and function.
    • Check jacket chiller or heating system for blockages or leaks.
    • Escalate unresolved issues to maintenance.

5.5 Post-Run Shutdown

  1. Turn off temperature control loop.
  2. Inspect and clean jacket circulation system if required.
  3. Document final reading and post-run status in Annexure-3.

6. Abbreviations

7. Documents

  1. Temperature Calibration Certificate – Annexure-1
  2. Bioreactor Temperature Monitoring Log – Annexure-2
  3. Final Temperature Shutdown Log – Annexure-3

8. References

9. SOP Version

Version: 2.0

10. Approval Section

Prepared By Checked By Approved By
Signature
Date
Name
Designation
Department

11. Annexures

Annexure-1: Temperature Calibration Certificate

Instrument ID Calibration Date Next Due Date Calibrated By
TRX-07 15/02/2025 15/08/2025 Sunita Reddy

Annexure-2: Bioreactor Temperature Monitoring Log

Date Time Setpoint (°C) Actual Temp (°C) Remarks
04/05/2025 10:00 37.0 37.1 Within range

Annexure-3: Final Temperature Shutdown Log

Batch ID Final Temp (°C) Time of Shutdown Operator
BR-105 36.9 19:30 Ajay Verma

Revision History:

Revision Date Revision No. Revision Details Reason for Revision Approved By
04/05/2025 2.0 Alarm handling and PID setpoint steps added GMP Compliance
Exit mobile version