Standard Operating Procedure for Protocol Amendment Approval Process in BA/BE Studies
Department | BA-BE Studies |
---|---|
SOP No. | SOP/BA-BE/019/2025 |
Supersedes | SOP/BA-BE/019/2022 |
Page No. | Page 1 of 13 |
Issue Date | 17/04/2025 |
Effective Date | 20/04/2025 |
Review Date | 17/04/2026 |
1. Purpose
To define the procedure for initiating, reviewing, approving, and implementing protocol amendments in BA/BE clinical studies, ensuring compliance with regulatory guidelines, Good Clinical Practice (GCP), and Ethics Committee (EC) requirements.
2. Scope
This SOP applies to all protocol amendments in ongoing or planned BA/BE studies sponsored or supported by the organization, including substantial and non-substantial changes impacting subject safety, data integrity, or study design.
3. Responsibilities
- Clinical Research Team: Identifies need for protocol change and drafts amendment.
- Medical Writer: Revises protocol document and synopsis with track changes and clean version.
- Regulatory Affairs: Prepares amendment cover letter and coordinates submission to EC and regulatory authorities.
- Quality Assurance: Verifies version control and maintains documentation in eTMF.
4. Accountability
The Clinical Trial Manager is accountable for ensuring that no changes to the protocol are implemented prior to approval by the EC/IRB and applicable regulatory authorities, unless necessary to eliminate immediate hazards to study subjects.
5. Procedure
5.1 Identification of Need for Amendment
- Document any required changes to protocol due to:
- New safety data
- Operational feasibility
- Regulatory feedback
- Scientific developments
- Record reason in Annexure-1: Amendment Justification Form.
5.2 Drafting the Protocol Amendment
- Medical Writer prepares:
- Revised protocol with tracked changes
- Clean revised version
- Updated synopsis (if applicable)
- Ensure new version number (e.g., V 2.0 to V 3.0) and revision date are applied.
5.3 Internal Review and Approval
- Circulate amendment for internal review by:
- Medical Affairs
- Biostatistics
- Clinical Operations
- QA
- Document internal sign-offs in Annexure-2: Internal Amendment Approval Log.
5.4 Ethics Committee and Regulatory Submission
- Submit amendment package including:
- Cover letter
- Revised protocol versions
- Highlight of changes
- Updated ICF (if required)
- Investigator communication
- Track submission and approval timelines in Annexure-3: Amendment Submission Tracker.
5.5 Implementation and Communication
- Upon approval:
- Notify sites and provide updated documents
- Train site personnel on changes
- Update all systems and databases
5.6 Archiving
- Store all versions and approval letters in the eTMF.
- Maintain amendment version history table in protocol appendix.
6. Abbreviations
- EC: Ethics Committee
- IRB: Institutional Review Board
- GCP: Good Clinical Practice
- eTMF: Electronic Trial Master File
- SOP: Standard Operating Procedure
7. Documents
- Amendment Justification Form – Annexure-1
- Internal Amendment Approval Log – Annexure-2
- Amendment Submission Tracker – Annexure-3
8. References
- ICH E6 (R2) – Good Clinical Practice
- USFDA – Protocol Amendments Guidance
- EMA – GCP Compliance Guidelines
9. SOP Version
Version: 2.0
10. Approval Section
Prepared By | Checked By | Approved By | |
---|---|---|---|
Signature | |||
Date | |||
Name | |||
Designation | |||
Department |
11. Annexures
Annexure-1: Amendment Justification Form
Date | Protocol No. | Change Summary | Reason for Amendment |
---|---|---|---|
10/04/2025 | BE/029/2024 | Change in PK sampling window | Scientific rationale update |
Annexure-2: Internal Amendment Approval Log
Department | Reviewed By | Date | Remarks |
---|---|---|---|
Clinical | Dr. Rajesh Mehta | 11/04/2025 | Approved |
Annexure-3: Amendment Submission Tracker
Submission Date | EC Name | Status | Approval Date | Remarks |
---|---|---|---|---|
12/04/2025 | IEC Pune | Approved | 15/04/2025 | Clean version filed |
Revision History:
Revision Date | Revision No. | Details | Reason | Approved By |
---|---|---|---|---|
15/01/2022 | 1.0 | Initial version | New SOP | QA Head |
17/04/2025 | 2.0 | Included tracker, eTMF reference, clarified substantial changes | GCP Alignment | QA Head |