Standard Operating Procedure for Emergency Protocol Activation in BA/BE Studies

Department BA-BE Studies
SOP No. SOP/BA-BE/134/2025
Supersedes SOP/BA-BE/134/2022
Page No. Page 1 of 9
Issue Date 17/04/2025
Effective Date 20/04/2025
Review Date 17/04/2026

1. Purpose

To define a clear and effective procedure for the activation and management of emergency protocols during the conduct of BA/BE studies in order to ensure immediate response, subject safety, and adherence to regulatory obligations.

2. Scope

This SOP is applicable to all staff at clinical and bioanalytical trial facilities involved in the conduct of BA/BE studies during any medical, technical, or environmental emergency.

3. Responsibilities

4. Accountability

The Clinical Operations Head is accountable for ensuring timely activation, documentation, and reporting of emergency procedures in accordance with regulatory and ethical guidelines.

5. Procedure

5.1 Definition of Emergency

  1. Medical emergencies (e.g., severe allergic reaction, cardiac arrest, seizures)
  2. Operational emergencies (e.g., power failure, equipment breakdown)
  3. Environmental hazards (e.g., fire, flooding, gas leaks)

5.2 Activation of Emergency Protocol

  1. Any staff member identifying an emergency must immediately inform the Medical Officer or PI.
  2. Activate Annexure-1: Emergency Protocol Activation Checklist.
  3. Use public announcement system or designated emergency signal where applicable.

5.3 Subject Management During Emergency

  1. Stabilize affected subject(s) using emergency equipment (e.g., oxygen, defibrillator).
  2. Move subject to designated emergency care room.
  3. Document event in Annexure-2: Emergency Incident Report Form.
  4. Inform local emergency medical services if required.

5.4 Evacuation and Site Safety

  1. Follow Annexure-3: Site Evacuation Plan in case of fire or environmental threat.
  2. Ensure all subjects and staff evacuate in an orderly manner.
  3. Assemble at pre-identified muster points and perform headcount.

5.5 Communication and Notification

  1. Notify:
    • Sponsor/monitor within 24 hours
    • IEC/IRB within the required reporting timeline
    • Regulatory authority (e.g., CDSCO) for SAEs or critical incidents
  2. Use Annexure-4: Regulatory Notification Form.

5.6 Post-Emergency Review and CAPA

  1. Conduct emergency debrief within 48 hours with all involved staff.
  2. Initiate CAPA using Annexure-5: Emergency CAPA Log.
  3. Review procedures to identify gaps or retraining needs.

6. Abbreviations

7. Documents

  1. Emergency Protocol Activation Checklist – Annexure-1
  2. Emergency Incident Report Form – Annexure-2
  3. Site Evacuation Plan – Annexure-3
  4. Regulatory Notification Form – Annexure-4
  5. Emergency CAPA Log – Annexure-5

8. References

9. SOP Version

Version: 2.0

10. Approval Section

Prepared By Checked By Approved By
Signature
Date
Name
Designation
Department

11. Annexures

Annexure-1: Emergency Protocol Activation Checklist

Step Description Status Initials
1 Identify and report emergency Completed SR
2 Alert medical response team Completed AV

Annexure-2: Emergency Incident Report Form

Date Time Type of Emergency Subject ID Description Action Taken
16/04/2025 11:30 AM Anaphylaxis SUB012 Allergic reaction post-dose Administered epinephrine

Annexure-3: Site Evacuation Plan

Zone Exit Route Muster Point Supervisor
Dosing Room North Stairwell Assembly Zone A Meena Joshi

Annexure-4: Regulatory Notification Form

Notified To Date Mode Details Sent Acknowledged By
IEC Chair 16/04/2025 Email SAE Report, PI statement Dr. Ramesh Kumar

Annexure-5: Emergency CAPA Log

Date Issue Root Cause Corrective Action Preventive Action Status
17/04/2025 Delayed response Alarm not triggered Manual alert issued Install new alert system Ongoing

Revision History:

Revision Date Revision No. Details Reason Approved By
05/01/2022 1.0 Initial SOP release Trial SOP setup QA Head
17/04/2025 2.0 Added structured annexures and evacuation protocols Inspection feedback QA Head