Standard Operating Procedure for Monitoring of Reaction Parameters in API Manufacturing
Department | API Manufacturing |
---|---|
SOP No. | SOP/API/022/2025 |
Supersedes | SOP/API/022/2022 |
Page No. | Page 1 of 11 |
Issue Date | 13/04/2025 |
Effective Date | 15/04/2025 |
Review Date | 13/04/2026 |
1. Purpose
To establish a procedure for consistent and controlled monitoring of critical reaction parameters during API manufacturing to ensure process safety, quality, and reproducibility.
2. Scope
This SOP applies to all chemical reactions conducted in reactor systems within the API manufacturing facility, including pilot and production scale operations.
3. Responsibilities
- Production Operators: Monitor and record reaction parameters as per BMR.
- Process Engineer: Ensure instruments are calibrated and parameter ranges are validated.
- QA Personnel: Review batch records for compliance with defined ranges and investigate any excursions.
4. Accountability
The Production Manager and QA Manager are accountable for ensuring the defined process parameters are maintained, documented, and investigated in case of deviations.
5. Procedure
5.1 Pre-Reaction Verification
- Confirm calibration status of temperature sensors, pressure gauges, pH meters, and timers.
- Review the BMR for specified setpoints and permissible tolerance limits for:
- Temperature
- Reaction time
- Pressure (if applicable)
- Agitation speed
- pH range (for aqueous/acid-base reactions)
- Ensure LOTO (Lockout Tagout) is not applied and reactor is safe to operate.
5.2 Parameter Monitoring During Reaction
- Temperature:
- Monitor using digital display or DCS interface.
- Record every 15 minutes during heating or cooling phase.
- Pressure (if applicable):
- Check gauge pressure continuously in case of closed systems.
- Log every 30 minutes during pressurized reactions.
- pH:
- Use calibrated pH meter and sample every 30 minutes or as specified in BMR.
- Record in the “Reaction Monitoring Log” (Annexure-1).
- Agitation:
- Set RPM as per BMR and observe for uniform mixing.
- Note any noise or unusual vibration and inform engineering immediately.
- Time:
- Note reaction start and end time with operator initials.
- Ensure minimum and maximum dwell times are followed.
5.3 Handling Excursions
- If any parameter exceeds the acceptable range:
- Pause the process if it poses safety risk.
- Document the deviation in the “Reaction Deviation Form” (Annexure-2).
- Inform the shift supervisor and QA immediately.
- Investigate root cause and implement corrective action before resuming process.
5.4 Documentation and Record-Keeping
- Record all observations in the BMR and “Reaction Monitoring Log.”
- Attach printed trends from automated systems (if available) for archival.
- Retain records as per documentation SOP and regulatory retention requirements.
6. Abbreviations
- SOP: Standard Operating Procedure
- QA: Quality Assurance
- BMR: Batch Manufacturing Record
- DCS: Distributed Control System
- LOTO: Lockout-Tagout
7. Documents
- Reaction Monitoring Log (Annexure-1)
- Reaction Deviation Form (Annexure-2)
- Calibration Certificates (Annexure-3)
8. References
- ICH Q7 – GMP Guidelines for Active Pharmaceutical Ingredients
- 21 CFR Part 211.100 – Written procedures and deviations
- ISPE Baseline Guide – Volume 6: Biopharmaceutical Manufacturing Facilities
9. SOP Version
Version: 2.0
10. Approval Section
Prepared By | Checked By | Approved By | |
---|---|---|---|
Signature | |||
Date | |||
Name | |||
Designation | |||
Department |
11. Annexures
Annexure-1: Reaction Monitoring Log
Time | Temp (°C) | pH | RPM | Pressure (bar) | Observed By |
---|---|---|---|---|---|
09:00 | 65.0 | 6.8 | 120 | 1.2 |
Annexure-2: Reaction Deviation Form
Date | Batch No. | Parameter | Deviation | Corrective Action | Approved By |
---|---|---|---|---|---|
13/04/2025 | API-202504 | Temp | Exceeded 70°C | Reduced heating rate |
Annexure-3: Calibration Certificates
Instrument | ID | Calibrated On | Due Date | Status |
---|---|---|---|---|
pH Meter | PH-002 | 01/04/2025 | 01/10/2025 | Calibrated |
Revision History:
Revision Date | Revision No. | Revision Details | Reason for Revision | Approved By |
---|---|---|---|---|
01/01/2022 | 1.0 | Initial Issue | New SOP | QA Head |
13/04/2025 | 2.0 | Added DCS and LOTO Requirements | Process Enhancement | QA Head |