SOP Guide for Pharma

The Ultimate Resource for Pharmaceutical SOPs and Best Practices

  • Home
  • Job Safety Analysis (JSA)
    • Oral Dosage Forms (Tablets & Capsules)
    • Oral Liquid Dosage Forms (Syrups, Elixirs, Suspensions, Emulsions)
    • Powder and Granule Dosage Forms
    • Topical Dosage Forms (Creams, Ointments, Gels, Lotions, Pastes)
    • Transdermal Dosage Forms (Patches)
  • Standard Test Procedures (STP)
  • SOP – Blog Post
  • Toggle search form

Aerosol: SOP for Validating Mixing Tanks Used in Formulation – V 2.0

Posted on By

Aerosol: SOP for Validating Mixing Tanks Used in Formulation – V 2.0

SOP for Validating Mixing Tanks Used in Formulation

Department Aerosol
SOP No. SOP/Aerosol/137/2025
Supersedes SOP/Aerosol/137/2022
Page No. Page 1 of Y
Issue Date 06/02/2025
Effective Date 16/02/2025
Review Date 06/02/2028

1. Purpose

The purpose of this Standard Operating Procedure (SOP) is to outline the procedure for validating mixing tanks used in the formulation of aerosol products. This SOP ensures that mixing tanks meet the required specifications and perform effectively to maintain the consistency and quality of the formulation. Validation of mixing tanks is essential to ensure that the proper mixing conditions, including time, speed, temperature, and homogeneity, are achieved and consistently maintained during production.

2. Scope

This SOP applies to all mixing tanks used in aerosol manufacturing, including those used for blending raw materials, propellants, and active ingredients. It covers the validation process to verify that the mixing tanks function as expected, ensuring that all specified parameters are met and that the mixing process does not affect the quality of the final product.

3. Responsibilities

  • Engineering Team: Responsible for overseeing the validation process for mixing tanks and ensuring that all tests are performed according to the defined procedures and specifications.
  • Production Team: Responsible for assisting with the validation process by performing the necessary tests and documenting the mixing process during
production runs.
  • Quality Assurance (QA) Team: Responsible for reviewing, approving, and ensuring that the validation protocol complies with GMP standards and regulatory requirements.
  • Maintenance Team: Responsible for ensuring the proper maintenance and calibration of the mixing tanks, and addressing any issues that arise during the validation process.
  • 4. Accountability

    The Manufacturing Manager is accountable for ensuring that the mixing tank validation process is carried out according to this SOP. The overall compliance with this SOP is overseen by the Quality Assurance (QA) Manager.

    5. Procedure

    5.1. Preparing for Mixing Tank Validation

    1. Ensure that the mixing tank is clean and free from any contaminants before starting the validation process.
    2. Verify that all necessary equipment for validation, including calibration tools, test products, and monitoring instruments (e.g., thermometers, flow meters), are available and functional.
    3. Review the manufacturer’s specifications and technical manuals for the mixing tank to understand the operating parameters that must be validated (e.g., mixing speed, temperature control, pressure limits).
    4. Establish the validation team, which should include members from the Engineering, Production, and QA teams.
    5. Ensure that the mixing tank is installed properly and is free of any mechanical defects that could affect its performance during validation.

    5.2. Conducting the Mixing Tank Validation

    1. Perform the following tests as part of the mixing tank validation process:
      • Mixing Speed Test: Verify that the tank’s mixing speed is adjustable and functions within the specified range. Test the speed using a calibrated tachometer or other suitable measurement devices.
      • Mixing Time Test: Verify that the specified mixing time is sufficient for achieving a homogenous mixture. Use sample collection at different time intervals during the mixing process to check for uniformity in the product.
      • Temperature Control Test: Verify that the mixing tank can maintain the required temperature throughout the mixing process. Use calibrated thermometers to check the temperature at multiple points within the tank during mixing.
      • Homogeneity Test: Verify that the formulation is homogeneous by taking samples from different locations in the tank and testing for consistency. The samples should be analyzed for uniformity of active ingredient concentration, viscosity, and other critical parameters.
      • Pressure Test: Verify that the tank can maintain pressure if the process requires it (e.g., in the case of pressurized mixing). Perform leak tests to confirm that the tank does not lose pressure during the mixing process.
    2. During testing, record all test results, including the test conditions, measured values, and any deviations observed. Document the results in the Mixing Tank Validation Report (Annexure-1).

    5.3. Documenting the Validation Results

    1. Document the following information in the Mixing Tank Validation Report (Annexure-1):
      • Mixing tank ID, model number, serial number, and location
      • The test parameters and conditions, including mixing speed, time, temperature, and pressure
      • The results of each validation test, including any deviations or non-conformities
      • The corrective actions taken to address any issues encountered during testing
      • The name and signature of the personnel performing the tests
      • The approval signatures from the QA team
    2. Ensure that the validation report is signed by the responsible personnel and reviewed by the QA team for accuracy and completeness.

    5.4. Reviewing and Approving the Validation Report

    1. The QA team should review the Mixing Tank Validation Report to ensure that all tests were conducted according to the protocol and that the tank meets the required specifications for performance.
    2. If any deviations are observed during the validation process, they should be documented in the Deviation Log (Annexure-2). Corrective actions should be implemented, and the tests should be repeated to verify the effectiveness of the corrective actions.
    3. The QA team should approve the report once all validation activities are complete and any deviations have been addressed.

    5.5. Finalizing the Validation Process

    1. Once the mixing tank is validated, it is considered qualified and can be used for regular production activities.
    2. All documentation, including the Mixing Tank Validation Report, Deviation Log, and any corrective actions, should be archived for future audits and inspections.
    3. Periodic revalidation and calibration activities should be scheduled as per the manufacturer’s recommendations and regulatory requirements.

    6. Abbreviations

    • GMP: Good Manufacturing Practice
    • QA: Quality Assurance
    • SOP: Standard Operating Procedure
    • CAPA: Corrective and Preventive Action
    • OQ: Operational Qualification
    • PQ: Performance Qualification
    • IQ: Installation Qualification

    7. Documents

    1. Mixing Tank Validation Report (Annexure-1)
    2. Deviation Log (Annexure-2)

    8. References

    This SOP is based on the following regulatory guidelines and industry standards:

    • Good Manufacturing Practice (GMP) Guidelines
    • FDA Code of Federal Regulations (CFR) Title 21, Part 211
    • International Council for Harmonisation (ICH) Guidelines

    9. SOP Version

    Version: 2.0

    10. Approval Section

    Prepared By Checked By Approved By
    Signature
    Date
    Name
    Designation
    Department

    11. Annexures

    Annexure-1: Mixing Tank Validation Report

    Equipment ID Model Number Serial Number Test Date Test Type Result
    MIX-001 Model A SN123456 06/02/2025 Mixing Speed Test Pass
    MIX-001 Model A SN123456 06/02/2025 Homogeneity Test Pass

    Annexure-2: Deviation Log

    Deviation ID Deviation Description Corrective Action Assigned To Status
    DEV-12345 Temperature deviation during mixing Recalibrated temperature control system Rajesh Patel Completed

    12. Revision History:

    Revision Date Revision No. Revision Details Reason for Revision Approved By Page No. Ref. Point No. Details of Revision
    01/01/2024 V 1.0 Initial Release First Issue Anjali Sharma Page 1 [Ref Point] First Release
    01/01/2025 V 2.0 Updated validation testing procedures To comply with updated GMP regulations Anjali Sharma Page 1 [Ref Point] Updated procedures
    See also  Aerosol: SOP for Conducting Valve Functionality Tests - V 2.0
    Aerosols V 2.0 Tags:Aerosol Batch Production, Aerosol Can Design, Aerosol Cold Filling, Aerosol Documentation Standards, Aerosol Emissions Control, Aerosol Environmental Regulations, Aerosol equipment calibration, Aerosol Filling Process, Aerosol Fire Safety Measures, Aerosol Formulation, Aerosol Good Manufacturing Practice (GMP), Aerosol Hazardous Materials Handling, Aerosol Incident Reporting, Aerosol Leak Testing, Aerosol Maintenance Schedules, Aerosol Personal Protective Equipment (PPE), Aerosol Pressure Filling, Aerosol Product Labeling, Aerosol Product Testing, Aerosol Propellant Selection, Aerosol quality control, Aerosol Regulatory Compliance, Aerosol Risk Assessment, Aerosol Safety Protocols, Aerosol Standard Operating Procedures (SOPs), Aerosol Storage Requirements, Aerosol Training Programs, Aerosol Valve Crimping, Aerosol Ventilation Systems, Aerosol Waste Disposal

    Post navigation

    Previous Post: API Manufacturing: SOP for Management of IPC Outliers and Investigations – V 2.0
    Next Post: Creams: SOP for Conducting FTIR Analysis of Cream Ingredients – V 2.0

    Standard Operating Procedures V 1.0

    • Aerosols
    • Analytical Method Development
    • Bioequivalence Bioavailability Study
    • Capsule Formulation
    • Clinical Studies
    • Creams
    • Data Integrity
    • Dental Dosage Forms
    • Drug Discovery
    • Environment, Health and Safety
    • Formulation Development
    • Gels
    • Good Distribution Practice
    • Good Warehousing Practices
    • In-Process Control
    • Injectables
    • Liquid Orals
    • Liposome and Emulsion Formulations
    • Lotions
    • Lyophilized Products
    • Maintenance Dept.
    • Medical Devices
    • Metered-Dose Inhaler
    • Microbiology Testing
    • Nanoparticle Formulation
    • Nasal Spray Formulations
    • Nebulizers
    • Ocular (Eye) Dosage Forms
    • Ointments
    • Otic (Ear) Dosage Forms
    • Pharmacovigilance
    • Powder & Granules
    • Purchase Departments
    • Quality Assurance
    • Quality Control
    • Raw Material Stores
    • Regulatory Affairs
    • Tablet Manufacturing
    • Rectal Dosage Forms
    • Transdermal Patches
    • Vaginal Dosage Forms
    • Validations and Qualifications

    Read SOPs in your Language:

     - 
    Bengali
     - 
    bn
    English
     - 
    en
    Gujarati
     - 
    gu
    Hindi
     - 
    hi
    Malayalam
     - 
    ml
    Marathi
     - 
    mr
    Punjabi
     - 
    pa
    Tamil
     - 
    ta
    Telugu
     - 
    te

    NEW! Revised SOPs – V 2.0

    • Aerosols V 2.0
    • Analytical Method Development V 2.0
    • API Manufacturing V 2.0
    • BA-BE Studies V 2.0
    • Biosimilars V 2.0
    • Capsules V 2.0
    • Creams V 2.0
    • Elixers V 2.0
    • Ointments V 2.0
    • Raw Material Warehouse V 2.0
    • Tablet Manufacturing V2.0

    New Publication: A must for All.

    Copyright © 2025 SOP Guide for Pharma.

    Powered by PressBook WordPress theme

    Go to mobile version