Skip to content
  • Clinical Studies
  • Pharma GMP
  • Pharma Tips
  • Stability Studies
  • Pharma Books
  • Schedule M

SOP Guide for Pharma

The Ultimate Resource for Pharmaceutical SOPs and Best Practices

  • Home
  • Job Safety Analysis (JSA)
    • Oral Dosage Forms (Tablets & Capsules)
    • Oral Liquid Dosage Forms (Syrups, Elixirs, Suspensions, Emulsions)
    • Powder and Granule Dosage Forms
    • Topical Dosage Forms (Creams, Ointments, Gels, Lotions, Pastes)
    • Transdermal Dosage Forms (Patches)
  • Standard Test Procedures (STP)
  • SOP – Blog Post
  • Toggle search form

Aerosol: SOP for Equipment Qualification in Aerosol Manufacturing – V 2.0

Posted on By

Aerosol: SOP for Equipment Qualification in Aerosol Manufacturing – V 2.0

SOP for Equipment Qualification in Aerosol Manufacturing

Department Aerosol
SOP No. SOP/Aerosol/112/2025
Supersedes SOP/Aerosol/112/2022
Page No. Page 1 of Y
Issue Date 06/02/2025
Effective Date 16/02/2025
Review Date 06/02/2028

1. Purpose

This Standard Operating Procedure (SOP) defines the process for equipment qualification in aerosol manufacturing. The objective is to ensure that all equipment used in the manufacturing of aerosol products is installed, operates, and performs as intended, and consistently meets the required specifications. Equipment qualification is a critical part of maintaining product quality and ensuring compliance with regulatory requirements.

2. Scope

This SOP applies to all equipment used in the manufacturing process of aerosol products at [Company Name]. It covers the qualification process, including Installation Qualification (IQ), Operational Qualification (OQ), and Performance Qualification (PQ), for all relevant manufacturing equipment.

3. Responsibilities

  • Maintenance Team: Responsible for ensuring that all equipment is properly installed, maintained, and calibrated according to manufacturer specifications.
  • Quality Assurance (QA) Team: Responsible for overseeing the qualification process, reviewing qualification protocols and reports, and ensuring compliance with GMP and regulatory guidelines.
  • Production Team: Responsible for providing equipment usage data, assisting with qualification tests, and verifying equipment performance during production.
  • Validation Team: Responsible for developing the qualification protocol, executing tests, and documenting the results for IQ, OQ, and PQ.

4. Accountability

The Manufacturing Manager is

accountable for ensuring that the equipment qualification is conducted according to this SOP. The overall compliance with this SOP is overseen by the Quality Assurance (QA) Manager.

5. Procedure

5.1. Equipment Qualification Process Overview

  1. The equipment qualification process consists of three stages:
    • Installation Qualification (IQ): Ensures that the equipment is installed correctly and meets the manufacturer’s specifications.
    • Operational Qualification (OQ): Verifies that the equipment operates as intended under specified conditions and that it meets the operational requirements.
    • Performance Qualification (PQ): Confirms that the equipment performs consistently and reliably during actual production conditions.
  2. Each stage of qualification must be documented and reviewed before moving to the next stage.
See also  Aerosol: SOP for Handling and Disposal of Cleaning Agents - V 2.0

5.2. Installation Qualification (IQ)

  1. Installation Qualification ensures that the equipment has been properly installed according to the manufacturer’s guidelines and specifications. The following activities should be performed during IQ:
    • Verify that the equipment is installed in the correct location, with appropriate utilities (e.g., power, water, air) connected.
    • Ensure that all safety features and control systems are in place and functional.
    • Confirm that all components are present, and installation is complete as per the manufacturer’s specifications.
    • Document any discrepancies in the installation and address them before proceeding to the next stage.
  2. The IQ report should include details such as:
    • Installation location
    • Equipment identification number
    • Calibration and verification results for key components
    • Any corrective actions taken

5.3. Operational Qualification (OQ)

  1. Operational Qualification ensures that the equipment operates within the defined parameters and meets the required functional specifications. The following activities should be performed during OQ:
    • Verify that the equipment operates as intended under specified conditions (e.g., temperature, pressure, speed).
    • Test and validate all critical process control parameters (e.g., filling accuracy, propellant charging, spray rate).
    • Ensure that alarms, safety systems, and error messages are functioning correctly.
    • Perform a series of tests to assess the equipment’s ability to perform under normal operating conditions.
  2. The OQ report should include:
    • Operational parameters tested
    • Test results for each parameter
    • Any deviations or non-conformities observed
    • Corrective actions taken to address deviations
See also  Aerosol: SOP for Monitoring Batch Yield During Production - V 2.0

5.4. Performance Qualification (PQ)

  1. Performance Qualification ensures that the equipment can consistently produce aerosol products that meet quality specifications over time. The following activities should be performed during PQ:
    • Run production batches to verify that the equipment performs as expected during actual manufacturing conditions.
    • Test the final product for quality attributes such as appearance, performance (e.g., spray rate, actuator function), and chemical composition.
    • Monitor equipment performance during production to ensure consistency and reliability.
    • Perform additional tests if required to confirm long-term performance.
  2. The PQ report should include:
    • Production batch data and test results
    • Performance data and verification against specifications
    • Analysis of any deviations or failures
    • Corrective actions taken to resolve any issues

5.5. Documentation and Record Keeping

  1. All equipment qualification activities should be documented and stored securely for future reference and regulatory review. The following records should be maintained:
    • Installation Qualification Report (Annexure-1)
    • Operational Qualification Report (Annexure-2)
    • Performance Qualification Report (Annexure-3)
    • Corrective Action Log (Annexure-4)
  2. Qualification records should be signed and dated by the responsible personnel. Records should be reviewed periodically to ensure they are complete and accurate.
  3. Qualification records should be retained for a minimum of 3 years or as required by regulatory guidelines.

5.6. Requalification

  1. If significant changes are made to the equipment (e.g., upgrades, repairs, or modifications), the equipment must undergo requalification to ensure continued compliance with the required specifications.
  2. Requalification should follow the same process as initial qualification and should include IQ, OQ, and PQ, as necessary.
See also  Aerosol: SOP for Conducting Final Leak Tests Before Packing - V 2.0

6. Abbreviations

  • GMP: Good Manufacturing Practice
  • QA: Quality Assurance
  • SOP: Standard Operating Procedure
  • RH: Relative Humidity
  • CFR: Code of Federal Regulations
  • OQ: Operational Qualification
  • PQ: Performance Qualification
  • IQ: Installation Qualification

7. Documents

  1. Installation Qualification Report (Annexure-1)
  2. Operational Qualification Report (Annexure-2)
  3. Performance Qualification Report (Annexure-3)
  4. Corrective Action Log (Annexure-4)

8. References

This SOP is based on the following regulatory guidelines and industry standards:

  • Good Manufacturing Practice (GMP) Guidelines
  • FDA Code of Federal Regulations (CFR) Title 21, Part 211
  • International Council for Harmonisation (ICH) Guidelines

9. SOP Version

Version: 2.0

10. Approval Section

Prepared By Checked By Approved By
Signature
Date
Name
Designation
Department

11. Annexures

Annexure-1: Installation Qualification Report

Equipment ID Installation Date Installation Location Verification Results Remarks
Aerosol-Fill-001 15/02/2025 Line 3 Compliant Ready for OQ

Annexure-2: Operational Qualification Report

Test Parameter Test Conditions Result Remarks
Filling Accuracy ±1% Pass Operates as expected

Annexure-3: Performance Qualification Report

Batch Number Test Date Result Remarks
Batch-001 17/02/2025 Pass Meets all quality specifications

Annexure-4: Corrective Action Log

Action ID Action Description Assigned To Completion Date Remarks
ACT-12345 Re-calibrated filling system Rajesh Patel 18/02/2025 Resolved accuracy issue

12. Revision History:

Revision Date Revision No. Revision Details Reason for Revision Approved By Page No. Ref. Point No. Details of Revision
01/01/2024 V 1.0 Initial Release First Issue Anjali Sharma Page 1 [Ref Point] First Release
01/01/2025 V 2.0 Updated qualification procedures To comply with updated GMP regulations Anjali Sharma Page 1 [Ref Point] Updated procedures
Aerosols V 2.0 Tags:Aerosol Batch Production, Aerosol Can Design, Aerosol Cold Filling, Aerosol Documentation Standards, Aerosol Emissions Control, Aerosol Environmental Regulations, Aerosol equipment calibration, Aerosol Filling Process, Aerosol Fire Safety Measures, Aerosol Formulation, Aerosol Good Manufacturing Practice (GMP), Aerosol Hazardous Materials Handling, Aerosol Incident Reporting, Aerosol Leak Testing, Aerosol Maintenance Schedules, Aerosol Personal Protective Equipment (PPE), Aerosol Pressure Filling, Aerosol Product Labeling, Aerosol Product Testing, Aerosol Propellant Selection, Aerosol quality control, Aerosol Regulatory Compliance, Aerosol Risk Assessment, Aerosol Safety Protocols, Aerosol Standard Operating Procedures (SOPs), Aerosol Storage Requirements, Aerosol Training Programs, Aerosol Valve Crimping, Aerosol Ventilation Systems, Aerosol Waste Disposal

Post navigation

Previous Post: BA-BE Studies: SOP for Handling Inquiries from Regulatory Agencies – V 2.0
Next Post: SOP for Validation of Measurement Systems

Standard Operating Procedures V 1.0

  • Aerosols
  • Analytical Method Development
  • Bioequivalence Bioavailability Study
  • Capsule Formulation
  • Clinical Studies
  • Creams
  • Data Integrity
  • Dental Dosage Forms
  • Drug Discovery
  • Environment, Health and Safety
  • Formulation Development
  • Gels
  • Good Distribution Practice
  • Good Warehousing Practices
  • In-Process Control
  • Injectables
  • Liquid Orals
  • Liposome and Emulsion Formulations
  • Lotions
  • Lyophilized Products
  • Maintenance Dept.
  • Medical Devices
  • Metered-Dose Inhaler
  • Microbiology Testing
  • Nanoparticle Formulation
  • Nasal Spray Formulations
  • Nebulizers
  • Ocular (Eye) Dosage Forms
  • Ointments
  • Otic (Ear) Dosage Forms
  • Pharmacovigilance
  • Powder & Granules
  • Purchase Departments
  • Quality Assurance
  • Quality Control
  • Raw Material Stores
  • Regulatory Affairs
  • Tablet Manufacturing
  • Rectal Dosage Forms
  • Transdermal Patches
  • Vaginal Dosage Forms
  • Validations and Qualifications

Read SOPs in your Language:

 - 
Bengali
 - 
bn
English
 - 
en
Gujarati
 - 
gu
Hindi
 - 
hi
Malayalam
 - 
ml
Marathi
 - 
mr
Punjabi
 - 
pa
Tamil
 - 
ta
Telugu
 - 
te

NEW! Revised SOPs – V 2.0

  • Aerosols V 2.0
  • API Manufacturing V 2.0
  • BA-BE Studies V 2.0
  • Capsules V 2.0
  • Creams V 2.0
  • Ointments V 2.0
  • Raw Material Warehouse V 2.0
  • Tablet Manufacturing V2.0

New Publication: A must for All.

Copyright © 2025 SOP Guide for Pharma.

Powered by PressBook WordPress theme

Go to mobile version